Manufacturing Process Of Vertical Suspended Pump

Mar 10, 2025 Leave a message

The manufacturing process of vertical suspended pump mainly includes the following steps:

Preparation work: Before installation, it is necessary to carry out unpacking inspection, measurement and layout, and preparation of construction organization design. Unpacking inspection requires the joint efforts of five parties (construction unit, owner, supervision unit, manufacturer, and design unit) to ensure that the parts to be installed are intact. The measurement and layout should strictly follow the designed elevation to determine the control points and place the longitudinal and transverse axes of the water pump. Preparation of construction organization design is the basis for ensuring the smooth progress of installation work.

Pump seat installation: The pump seat needs to be buried in concrete. The installation sequence includes hoisting the pump seat into the pit, threading the anchor bolts, aligning the inner hole of the embedded parts, adjusting its elevation and level with a level and a box level, tightening the anchor bolts, checking the concentricity, elevation and level, and then pouring the second phase concrete.

Pump body installation: After the second phase concrete hardens, the pump body is installed. The specific steps include lifting the trumpet, impeller assembly, impeller housing assembly and guide vane assembly into the forebay with an electric hoist, lifting the 60° elbow and placing it on the intermediate pipe to tighten it, then connecting the pump coupling to the pump shaft, lifting it into the bearing end face of the 60° elbow, lifting the guide vane assembly through the pump shaft and connecting it to the intermediate pipe, fixing the impeller assembly and measuring the gap between the blade and the housing to make it uniform, and finally installing the trumpet.

‌Vibration testing and troubleshooting‌: Vertical suspended pumps are susceptible to resonance conditions caused by the coincidence of the operating frequency and the natural frequency of the pump structure, resulting in vibration problems. To avoid these problems, vibration testing is required on the pump manufacturer's test bench and pre-operation vibration testing is required on site. By monitoring the vibration of the pump under steady-state and transient conditions, the root cause of excessive vibration can be diagnosed and appropriate corrective measures can be taken.